This Project report entitled Pre-Feasibility Study of Upper Balephi Khola Hydroelectric Project,Sindhupalchowk. We the students of 4th year of Civil Engineering of Kantipur Engineering college jointly completed the project on 4 months of time period. We visited the site studied the background, area, location, access, catchment areas ,transmission route, hydrology, geology for project. Then desk study, Map study, Design of the various structures were done. Design discharge at 50th percentage of time was 21.84,net head 47.5 m available power 89.10 Mw, available energy 60.60 Gwh were calculated. ...